January Fabrication Progress1/26/2022 Throughout the month of January the steel bridge was being fabricated. It began by cutting all the 2 foot and 3 foot members for the top and bottom of the stringers. The vertical pieces were cut for the stringers as well. All these members were cute 1/8" longer than specified in the plans. The X pieces in the middle of the stringers were cut to size and then their angles were cut at 30 or 20 degrees depending on the 2 foot or 3 foot section. The vertical and horizontal stringer members were cut to their exact length. The x-connection plates and horizontal stringer connection plates were cut with the waterjet machine. The vertical member connection T-plates were spot welded to the vertical members for the stringers.